B4 12er NORD & Ski brIDGE
The new construction of the 12er NORD promises an absolute improvement in comfort. The existing lift with stand-up gondolas from 1989 will be replaced by a 10-seater monocable gondola lift - identical in construction to the 12-seater KOGEL lift. The valley station is moving into the valley and a new ski bridge over the main road will provide convenient and safe access directly to the two stations of the Hochalmbahn and 12er NORD. The ascent is rapid with a transport capacity of 2,600 people per hour. Once you reach the top, you have a difficult decision to make - continue on the Skicircus circuit or take the 12er Nord downhill run into the valley.
Facts:
- System type: 10 EUB - Doppelmayr company
- Start of construction: April 2024
- Completion: November 2024
- Capacity: 2,600 persons per hour
- Length: 1936 m
- Speed: 6,5 m/sec
- Height difference: 875 m
- Travel time: 6,51 min
- Number of cabins: 56
F1+F2 STREUBÖDEN
HELLO! The old one is leaving. The new one is coming.
The Fieberbrunn cable car to the Lärchfilzkogel will be getting a new model in summer 2024: a single-cable gondola lift, 10-seater, non-stop to the top, panoramic windows, more modern, faster, more comfortable and with a sleek red. A milestone for Fieberbrunn, a new lift highlight for the Home of Lässig!
FACTS
- System type: 10 EUB - Doppelmayr company
- Start of construction: April 2024
- Completion: December 2024
- Transport capacity: 2,500 passengers per hour
- Inclined length: 3013 m
- Speed: 6 m/sec
- Height difference: 806 m
- Travel time: 8.5 min
- Number of cabins: 95